
The team finished paving last week on the I-80 Keystone to Stateline project – a huge milestone for the project! The project started in May 2018 and is scheduled to be completed at the end of this year. Q&D is mostly finished with our self-preform work, and our subcontractors are now in the final stages of striping and installing guardrail. Flashing “Wrong Way” signs are being tested and installed.
Check out these stats!
- Throughout the project 162,500 tons of dense grade pavement and 36,702 tons of open grade pavement was used.
- Over 35 lane miles were paved this summer.
- Over 19,000 paving hours worked this summer!