This lateral included seven miles of 6-inch pipe to replace an existing pipeline in this rural community. During pressure testing, crews found a manufacturer’s defect in the pipe which was hidden by the factory applied coating. Our team located the defect and made the repair while delivering the project without delaying the scheduled completion date.
Project Overview
Location
Battle Mountain, NV
Designer
Southwest Gas Corporation
Delivery Method
Design-Bid-Build