5 Ridges Housing Development
The ongoing development of the 5 Ridges master planned community stakes claim to one of the largest dirt spreads in the Reno-Sparks area. As of January 2024, Q&D Construction is nearly finished moving the original 3 million-plus yards of dirt.
The new housing community will be home to between 1,200 and 1,800 single family homes, 126 townhomes, parks, and a trail system. Nestled in the valley near Highland Ranch Parkway and Pyramid Way, 5 Ridges has been likened to Somersett’s little brother.
5 Ridges broke ground in late February 2021, with a massive effort that is moving quickly. Model home construction started in late 2023.
Keys To Construction
For a site of this magnitude, Q&D brought a phased approach designed to release the completed villages to the home constructors as early as possible. Continued development of subsequent villages will progress as homes were being built on the completed portions, allowing our clients to quickly market their new lots. Seven of the 10 villages are planned for 5 Ridges, with the final three still in development by the site owner.
The client was adamant about quick turnaround for the site, so Q&D began 6-day work weeks with longer hours to expedite the cut-and-fill process for this massive area. Although the site was expansive, Q&D met many challenges in tight quarters through the center of the canyon just off the main entry. Utility installation crews were busy handling the underground work while the soil-nail walls were being placed along the slopes. Both tasks continued while material hauling progressed on the main road, creating a challenging window for all facets of work.
Onsite Crushing Operation
The site lends itself to mobile crushing opportunities, allowing Q&D to make aggregate base and drain rock onsite. This saved both time and money in material hauling and expedited the overall site work. Q&D is no stranger to assembling mobile crushing plants on the site of large earthwork projects. The time savings alone at 5 Ridges offers the project owner quicker access to their finished lots, and it creates logistical flexibility for Q&D crews throughout the project.
Landmark Dirt Moving
Q&D has moved more 3 million cubic yards of dirt in preparation for the new master-planned community. Check out some of the intricate details during this period:
- The maximum amount of dirt moved in a single shift during this period was a whopping 22,000 cubic yards.
- Average cubic yards per shift is 10,500.
- Nearly all dirt was moved through truck hauling, with distances up to 4,000 feet.
- Crews totaled more than 55 craftsman site wide — with only 21 dedicated to dirt moving.
Upcoming Project Components
Looking back, Q&D has poured all curb, gutter and sidewalk for the site as well as the asphalt paving throughout the new development. This includes installation of three roundabouts.
"Q&D Construction played the key role in completing the first phase of this $750 million residential project. Its work as the prime GC was instrumental in its completion of the main backbone, civil and underground work, setting the base for homebuilders to construct in the valley's most recent master planned community. Q&D's professionalism, problem-solving approach and responsiveness were key to the project's success, ensuring challenges were addressed efficiently, timelines were met and high-quality infrastructure was delivered.
I appreciate the effort and excellent work Q&D provided throughout construction of this regional project and cannot emphasize how much we recommend Q&D. "G. Blake Smith - Managing Director S3 Development Company
Project Overview
Location
Spanish Springs, NV
Client
S3 Development
Completion Date
Scheduled Completion - Fall 2022
Delivery Method
Negotiated GMP