It’s a Busy Time for Concrete
Over the last 30 days, Q&D’s concrete crews have been very busy!
Reno-Tahoe International Airport: Crews poured an average of 130 truck loads of concrete on 4 nights for a total of over 5200 cubic yards.
Vista Blvd., Sparks NV: Crews placed 7500 feet of 10’ wide sidewalk in just 3 days!
Caltrans Donner Scale Project: Crews poured 1200 cubic yards in 2 nights of a 9 ½” base slab that was screeded by hand and
then topped with a 12 ½” paving slab also poured in 2 nights.
NDOT Pryamid Way, Sparks, NV: Crews poured and finished 3000 lineal feet of island curb on the NDOT’s Pyramid project. This also included all concrete paving between the curbs.
GREAT JOB to Everyone Involved!
June 25, 2010