Latest News

It’s a Busy Time for Concrete

Over the last 30 days, Q&D’s concrete crews have been very busy!

Reno-Tahoe International Airport: Crews poured an average of 130 truck loads of concrete on 4 nights for a total of over 5200 cubic yards.

Vista Blvd., Sparks NV: Crews placed 7500 feet of 10’ wide sidewalk in just 3 days!

Caltrans Donner Scale Project: Crews poured 1200 cubic yards in 2 nights of a 9 ½” base slab that was screeded by hand and
then topped with a 12 ½” paving slab also poured in 2 nights.

NDOT Pryamid Way, Sparks, NV: Crews poured and finished 3000 lineal feet of island curb on the NDOT’s Pyramid project. This also included all concrete paving between the curbs.

GREAT JOB to Everyone Involved!

Assumption Church Breaks Ground

After two years of planning Q&D broke ground on the Assumption Church Project on June 14th in Truckee, CA. The project will include sitework and a new Church/Parish Center. This space will be exclusively used as the Parish Center once the new church is built at a later date. The worship space will include three large timber trussess and exposed beams. Project is scheduled for an Easter 2011 Grand Opening!

RECENT ENTRIES: Previous Page
Latest News

Monday August 23rd
Q&D is getting ready to begin work on the NDOT D2-0410-10 Bridge Deck Structures Rehabilitation project. This project will consist of repairing eight (8) bridges on I-80 and US 395 in the Reno, Sparks and Verdi areas. The repair work will include...

next

Thursday August 12th
This August, Q&D is the recipient of the Silver Shovel Award from Underground Service Alert (USA) North for having the most USA dig tickets with NO utility strikes. USA North is the agency that tracks and identifies underground utilites for...